1. ATTENTION returning members. If you are coming here from the old forum for the first time, you will need to reset you password. However, we had an email problem getting password reset links set out to a lot of the email addresses. That problem is temporarily rectified but IF you still have an issue, email me direct at info@thebuildingcodeforum.com and I will give you a temporary password.
    Dismiss Notice
  2. Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by clicking here: Upgrades
    Dismiss Notice

Fast Track Projects

Discussion in 'Plan Review Topics' started by redbird11, Mar 19, 2019.

  1. redbird11

    redbird11 Sawhorse

    Joined:
    Apr 10, 2018
    Messages:
    16
    Likes Received:
    0
    Hello,
    I am most familiar with the design-bid-build process, but am now beginning a design/build project with multiple fast track document issuances. I have been advised to meet with the plans examiner earlier than usual to discuss the way the documents are packaged. Anyone have experience/advice on the best approach for packaging documents for this delivery method? And managing revisions?
     
  2. cda

    cda Sawhorse

    Joined:
    Oct 19, 2009
    Messages:
    15,608
    Likes Received:
    950
    Find out first if they fast track?
     
  3. TheCommish

    TheCommish Sawhorse

    Joined:
    Sep 27, 2011
    Messages:
    775
    Likes Received:
    100
    don't let them push you.
    It is our option to issue permits in part not a mandatory requirement.
    So my take is it all depends on my comfort level of the project team, I will not issue foundation permit unit till the code summary pages the floor plans and structural steel and document to confirm lift safety system are though out.
    Remember lack of planning on there part does not constitute an emergency on my part, and once you issue a permit it is hard to take it back.
     
    tmurray and my250r11 like this.
  4. TheCommish

    TheCommish Sawhorse

    Joined:
    Sep 27, 2011
    Messages:
    775
    Likes Received:
    100
    I was talking with an RDP today and he wants to know if the project was fast track, does he get double the fee? and what project was not considered fast track anymore?
     
  5. mtlogcabin

    mtlogcabin Sawhorse

    Joined:
    Oct 17, 2009
    Messages:
    7,108
    Likes Received:
    745
    For every project you "Fast Track" you will put 3 projects on the "Slow Track"
     